In short: 8 steps
- Waterproof the plinth vertically and horizontally and build a Z-shaped cavity tray into the bed joint.
- Insulate the plinth zone with XPS boards under the cavity tray.
- Dry-lay the first course, set the corner bricks and the string line.
- Leave every second perpend open in the course above the tray: these are the weep vents.
- Fit mineral wool in two staggered layers and fix it with wall ties set into the bed joint.
- Fill the joints completely with mortar and keep the cavity clean.
- Point the joints once the mortar passes the “thumb test”, then brush the brickwork.
- Cover the brickwork during breaks. Trim the excess tray membrane when the work is finished.
Diagram of a cavity wall with brick facing
A three-layer wall with facing brick lasts for decades when every layer does its job: the load-bearing wall carries the loads, insulation keeps the heat in, the ventilated cavity removes moisture, and ProKeram facing bricks protect the facade from rain, frost and UV.
- Facing brick, half-brick leaf (120 mm).
- Ventilated cavity, 30–40 mm.
- Insulation: mineral wool boards in two staggered layers.
- Load-bearing wall of common brick or ceramic block.
- Wall tie with an insulation retaining disc.
- Z-shaped cavity tray: drains water from the cavity to the outside.
- XPS boards in the plinth zone and vertical bitumen waterproofing.
- Open perpend: air inlet and water outlet.
- Plinth courses. The course above the tray projects about 1 cm.
Preparation: bricks, mortar, tools
Which bricks to use for a facade
An external wall needs bricks with frost resistance of at least 35 cycles. ProKeram facing bricks have 50–100 freeze-thaw cycles, compressive strength of 150–250 kgf/cm² (15.0–25.0 N/mm² under current standards) and water absorption of 4 to 8.5%. Specifications for each colour are on the red, cream and chocolate brick pages.
A half-brick facing leaf takes 51–52 bricks of 250×120×65 mm per 1 m² including 10 mm joints. Order the full quantity from one batch.
Before you start
- Dry-lay the first course to set out the perpends and avoid unnecessary cutting at corners and openings.
- Take bricks from several pallets at once and diagonally across each pallet so the shades are spread evenly over the facade. This matters most for Bavarian masonry.
- Choose mortar to suit the brick’s water absorption: facing brickwork uses dedicated masonry mortars for face bricks.
- Prepare a gauge rod marked with course heights, a string line, a spirit level, a trowel, a timber joint-width gauge, a jointer or a piece of hose, and a soft brush.
Plinth waterproofing and insulation
Facing work starts when the load-bearing wall is built and the plinth is protected from moisture.
- Vertical waterproofing is a bitumen coating on the outside of the plinth.
- Horizontal damp-proof course is a membrane under the first course of the load-bearing wall.
- Z-shaped cavity tray is a membrane strip with one edge built into the load-bearing wall and turned up. The other edge will later sit in a bed joint of the facing leaf.
The plinth zone is insulated with extruded polystyrene (XPS). The boards are bonded with mastic in two staggered layers under the tray. Their top edge is bevelled so water runs outwards instead of sitting on the insulation.
How to lay the cavity tray correctly
- Spread a layer of mortar on the bricks first, then lay the membrane. It must sit inside the joint, not under it.
- The membrane lies flat, without folds, falling outwards so water can drain freely.
- Laps are at least 20 cm and bonded.
- At corners the membrane is cut to size and welded with a heat gun.
- Do not trim the projecting edge until the end of the job: it shows that the tray runs around the whole perimeter.
First course and weep vents
Brickwork starts at the corners. The corner brick is levelled, a gauge rod with course heights is fixed at the corner and the string line is stretched. On long walls the line can be fixed straight to the finished corner.
The course above the cavity tray projects about 1 cm in front of the plinth. This forms a drip so water from the facade does not run onto the plinth brickwork.
How to make weep vents
In the course above the tray, every second perpend is left without mortar. Air enters the cavity and condensed water drains out through these openings. Open perpends are also left in the top course under the roof and below window sills so air moves from bottom to top. Mortar is cleared out of the vents down to the membrane with a timber gauge or a jointer, and no mortar droppings should remain behind the brickwork.
Joint width is checked with a timber gauge: 10–12 mm for bed joints and 10 mm for perpends is recommended. All other perpends are filled with mortar completely.
Insulation and wall ties
Above the plinth, the insulation is mineral wool. The edge of the bottom board is trimmed so it fits tightly against the cavity tray without cold bridges.
- Boards go in two staggered layers so the second layer covers the joints of the first.
- Fix insulation only up to the height you will brick up the same day. The brickwork protects the wool from rain and damage.
- Boards are held by retaining discs on the wall ties.
How to install wall ties
A wall tie connects the load-bearing wall to the facing leaf. It must be horizontal and enter a bed joint of the facing brickwork, fully embedded in mortar. Usually at least 4–5 ties per 1 m² are used, with closer spacing at corners, openings and along the top of the wall. The exact number and type are set by the project design.
Filling the joints and keeping the cavity clean
Only brickwork without voids in the joints protects a facade from driving rain. To fill a perpend well, butter the end of the brick with enough mortar and press it against its neighbour. If you lift a freshly laid brick, the mortar should have bonded over its whole surface.
- Bed joints are filled across the full width of the brick.
- Mortar squeezed onto the face is removed with the trowel at once.
- Mortar squeezed towards the insulation is carefully removed: droppings in the cavity bridge moisture across and block the airflow.
- Mortar splashes are cleaned off the bricks before they harden.
Keep checking course heights against the gauge rod and level the corner brick before each new course. Above 1.2–1.5 m, work from scaffolding.
Pointing: when and how
Joints are pointed when the mortar has set evenly but is still workable. Use the “thumb test”: if your thumb leaves a deep print and the mortar sticks, it is too early; if the print is barely visible, it is time.
- For a smooth concave joint, use a piece of rubber hose or a jointer of the right profile. The pressure compacts the mortar and improves its bond with the brick.
- At corners, tool the joint from the corner towards the wall so the mortar is pressed in.
- Where fresh mortar meets mortar that has already set, work from the fresh towards the set mortar.
- If a joint is not dense enough, fill it with more mortar without leaving voids.
After pointing, brush the brickwork diagonally with a soft brush: this removes mortar residue from the bricks and joint intersections without damaging the joints. Mortar colour (white, grey or black) changes the look of a facade as much as the brick colour. See examples on each ProKeram facing brick page.
Protecting the brickwork and finishing the job
- Cover the brickwork during breaks. Fresh brickwork and exposed insulation are covered with sheeting held by a batten and hooks. Rain washes mortar out of fresh joints and soaks the mineral wool.
- Trim the cavity tray only after the brickwork is finished. Its edge stays just visible under the projecting course above the plinth.
- The drainage board at the plinth is covered with geotextile that also wraps its top edge. The geotextile is spot-bonded with solvent-free bitumen adhesive so the pores do not clog.
- Protect the weep vents from insects and leaves: the simplest way is to push a piece of reinforcing mesh into the open perpends. More reliable are plastic weep vents for brickwork that reach the insulation.
Common mistakes in facing brickwork
No weep vents
A cavity without open perpends at the bottom and top is not ventilated, and moisture builds up in the insulation.
Mortar in the cavity
Droppings and brick offcuts behind the facing carry moisture to the insulation and the inner wall.
Empty joints
Unfilled perpends let driving rain in and break down in frost.
Folds in the tray
Water collects in the folds of the cavity tray and flows inwards instead of out.
Bricks from one pallet
Bands of different shades on the facade. Mix bricks from several pallets.
Brickwork left open to rain
Washed-out mortar, efflorescence and wet insulation. Cover the work at every break.
Basic rules for choosing bricks and mortar are also covered in “Masonry technology”, and the rules for laying mixed shades in “Bavarian masonry”.
Frequently asked questions
How wide should the cavity between insulation and facing brick be?
30–40 mm. A narrower cavity ventilates poorly and is easily blocked by mortar droppings.
How many weep vents does facing brickwork need?
Every second perpend is left open in the course above the cavity tray, and vents are also made in the top course so air moves from bottom to top.
How thick should the joints be in facing brickwork?
Bed joints are 10–12 mm and perpends are 10 mm. The joint should not be recessed more than 2 mm from the brick face.
How many wall ties are needed per 1 m²?
Usually at least 4–5 ties per 1 m², with more at corners, openings and along the top of the wall. The exact number is set by the design.
When should brick joints be pointed?
When the mortar has set evenly but is still workable: your thumb leaves a barely visible print and the mortar does not stick.
Can facing bricks be laid without insulation?
Yes, if the thermal calculation for the wall allows it. A ventilated cavity and weep vents are still needed so moisture does not build up behind the facing.